CASE STUDIES
case studies
Malls & SHOPPING CENTRES
PROJECT REFERENCE
MANDINI SPAR
Problem to be solved:
Customer was paying over R 30 000 per week for tankers to supply water when municipal water supply failed.
Borehole treatment system was designed and built within 4 weeks.
Client: Spar Shopping Centre
Location: Durban
Capital Cost: R 1 100 000 ExVAT
Operating Cost: R10 per kL (Excluding power consumption)
Plant Capacity: 150 000 L per day
Reduced water cost
Consistent and reliable water quality
PROJECT REFERENCE
MALL
Problem to be solved:
Frequent down time of municipal water supply resulting in no water to the mall.
Surface and rain water treatment system provides water supply from alternative water sources.
Client: Eastgate Mall
Location: Bedfordview
Capital Cost: R 1 350 000 ExVAT
Operating Cost: R8 per kL (Excluding power consumption)
Plant Capacity: 120 000 L per day
Frequent down time of municipal water supply resulting in no water to the mall.
Surface and rain water treatment system provides water supply from alternative water sources.
Constant and reliable water supply for the mall
Reduced water cost
Consistent and reliable water quality
PROJECT REFERENCE
Shopping Centre
Problem to be solved:
Client: Cornerstone Shopping Centre
Location: Rustenburg, SA
Capital Cost: R330 000 ExVAT
Operating Cost: R10 per kL (Excluding power consumption)
Plant Capacity: 80 000 L per day
Water Source: Borehole